Construction Activities March 31 - April 5
Construction Activities March 31 - April 5
​
Work Hours:
​
Hancock Village Dr- 7:00- 5:00 Monday - Friday, Saturday 8:30-6:00
Puddingstone- 7:00- 5:00 Monday - Friday, Saturday 8:30-6:00
***All work outlined below are approximations of time to conduct activities, weather dependent and subject to change. We will keep this updated to the best of our ability with any significant changes in duration and activities***
Please refer to the “Timeline Map” tab above that shows the locations of the buildings.
Hancock Village Drive
-
This week working Monday through Friday & Saturday
-
Construction activities ongoing, with equipment operating and trucks coming and going from the site.
Puddingstone
-
This week working Monday through Friday & Saturday
-
Blasting is complete except if more rock is found during utility excavation
-
Site work activities ongoing
-
Ongoing activities include: placing of concrete slabs, wood framing and interior and exterior building work.